Digging In: Construction

Digging In: Construction Update

Digging In: Construction Update

"Like all of our weekly construction meetings, I am always fascinated in listening to the discussion about detail changes these guys are making as this project progresses. All vital moves that are being taken as the building takes form, making adjustments to accommodate PVC pipes whose location impacts placement of beams, existing windows that affect placement of steel, center where there was a structural dividing wall and therefore no existing pier. All worked out but with alot of creative input from Dan Godfrey, our steel guy; John Tracey and Kerry Caparulo from Scope; and our architect, David Shaughnessy."  - Ellen